xAI's Colossus passes 300 megawatts in Memphis

With 150,000 H100 and 50,000 H200 chips online, Epoch AI estimates the Memphis training cluster at about 360 MW of facility power, the first U.S. AI site it tracks past 300 MW.

Step chart of estimated facility power at the largest U.S. AI data centers through February 2025, with Colossus 1 highlighted at about 360 megawatts
Estimated facility power of the largest U.S. AI data centers, through February 17, 2025. Chart: SI USA, from Epoch AI data / Data CC BY 4.0 · License

Colossus ran its first large training job in August 2024 on 25,000 H100s and reached 100,000 by September. Epoch AI’s estimates combine company chip counts with satellite imagery, permits and utility filings.

Index treatment. One-gigawatt training cluster in operation moves to 0.5.